Project PRSE I

Project PRSE I

This component of the World Bank-financed Power Sector Recovery Project has two components :

  1. Supply, installation, testing and commissioning of materials and equipment for the rehabilitation and extension of the MV/LV distribution network of the municipality of Dixinn ;
  2. Supply and installation of materials and equipment for the rehabilitation of connections and the improvement of technical conditions for the connection of makeshift networks in the Kaloum, Ratoma and Matoto areas.
  • COUNTRY: GUINEA
  • RECIPIENT: EDG (Electricité de Guinée)
  • DURATION OF THE PROJECT: 18 MONTHS